Using Force Majeure/Frustration to Escape Contracts in Singapore

Last updated on March 18, 2020

man tearing contract

If you have signed a contract in Singapore agreeing to do something but find yourself unable to do it due to circumstances that are entirely beyond your control and that you could not have foreseen, then you may be able to get out of those obligations, at least for a while, by invoking the concepts of force majeure or frustration.

Force Majeure

What is force majeure?

Force majeure is a clause that is frequently included in commercial contracts that allows a party to be excused from performing its obligations on time when some unforeseen outside event beyond the parties’ control (also known as a force majeure event) prevents or delays performance.

How might a typical force majeure clause be worded?

How a force majeure clause works depends entirely on how it is worded and there are a wide variety of potential formulations. Typically though, a force majeure clause lists:

  • Specific kinds of situations that would amount to a force majeure event. For example, civil commotion, riot, labour strike, act of government, act of God, natural disaster, pandemic, etc.;
  • A procedure for the parties to declare that a force majeure event has occurred (see below); and
  • Consequences for when such an event occurs. For example, an extension of time for the affected party to perform its obligations, and a right for the other party to cancel the contract if the affected party remains unable to perform its obligations at the end of that extended period of time.

How can a force majeure clause be invoked?

Sometimes a force majeure clause will prescribe a specific procedure for a party to invoke the clause. Otherwise, usually one party simply writes to the other informing them that a force majeure event has occurred and explaining how this has impacted the party’s ability to perform its obligations.

For an event to be accepted as a force majeure event, it is usually not enough to show that it has merely become more difficult or more expensive for the party to discharge its obligations (e.g. the price of raw materials or labour has increased). Usually it must be impossible or highly impracticable for the party to perform its obligations, but again this depends on the wording of the clause.

For example, if the clause is worded such that a force majeure event must “prevent” the performance of the affected party, then the clause may only be capable of being invoked if an event has happened that caused such performance to become impossible to perform.

On the other hand, if the clause states that a force majeure event must “hinder” the performance of the affected party, then the event in question only needs to render performance more or less difficult, instead of impossible, for the clause to be invoked.

What happens if force majeure is successfully invoked?

This depends on the wording of the clause but often, it merely grants the affected party an extension of time to perform its obligations. It seldom compensates the affected party for any increased costs of doing so.

Sometimes it will excuse the affected party from performing at all and allows the other party to cancel the contract.

Frustration

What is frustration?

Frustration is probably what you will need to rely on if you don’t have a force majeure clause in your contract and a major unforeseen event beyond your control prevents you from discharging your contractual obligations.

In Singapore, the Frustrated Contracts Act relieves parties from their duty to discharge their contractual obligations if it has become impossible to perform them.

How is frustration different from force majeure?

Force majeure can only be invoked if a force majeure clause is included in your contract. On the other hand, you can claim that your contract has been frustrated on the basis of the Frustrated Contracts Act, even if there is no force majeure clause in your contract.

In addition, the consequences of a contract being frustrated may differ from the consequences of some force majeure clauses (as discussed further below).

When might a contract become frustrated?

The circumstances in which a contract might become frustrated are likely to be similar to typical force majeure scenarios. But because the Frustrated Contracts Act does not define specific triggering events, there is more scope to argue that a certain event has frustrated your contract, than could be argued pursuant to a tightly-drafted force majeure clause (i.e. that has specifically stated the kinds of situations that would constitute force majeure events).

In general, if the event makes it impossible or extremely difficult for you to perform your contractual obligations, with certain exceptions, this is likely to frustrate your contract.

What happens if a contract becomes frustrated?

When a contract is frustrated, it is essentially cancelled. Neither party needs to do anything more for the other. There is no need to pay any sums set out in the contract. If any payments have already been made but not used to provide goods or services, a refund or partial refund may be obtainable.

The Frustrated Contracts Act gives discretion to the courts to determine the most equitable manner of cancelling the contract and ensuring that neither party unjustly benefits from the cancelled contract at the other’s expense, as far as possible.

If an external event has impacted your ability to perform certain contractual obligations in Singapore, consult a lawyer immediately. This is a very complex area of law and it is important that you have reliable legal advice early on so that you act in a way that preserves your rights without putting you in breach of contract.

Not every event that has a negative impact on your business will entitle you to cancel a contract. So much depends on the wording of your contract and the specifics of your case. It is best that you consult a lawyer immediately if you think you may need a legal basis to get out of a contract.

Business Contract Guides
  1. Your Guide to Non-Disclosure Agreements in Singapore
  2. Your Guide to Employment Agreements in Singapore
  3. Your Guide to Tenancy Agreements in Singapore
  4. Your Guide to Shareholder Agreements in Singapore
  5. Your Guide to Partnership Agreements in Singapore
  6. Your Guide to Distributor Agreements in Singapore
  7. Your Guide to Consultancy Agreements in Singapore
  8. Your Guide to Freelance Service Agreements in Singapore
  9. Your Guide to Service Agreements in Singapore
  10. Your Guide to Business Referral Agreements in Singapore
Singapore Contract Law
  1. How to Change (or Amend) a Contract in Singapore
  2. How to Legally Use E-Signatures in Singapore Contracts
  3. Privity of Contract & When a Third-Party Can Sue You in Singapore
  4. How to Properly Draft a Contract in Singapore (DIY Guide)
  5. How to Recover Damages For Breach of Contract in Singapore
  6. Enforcing Verbal Agreements in Business Contracts
  7. Dispute Resolution Clauses in SME Contracts: Why You Need Them
  8. Requisite elements in the formation of a contract
  9. Entire Agreement Clauses in Singapore: What are They and What Do They Do?
  10. Guide to Indemnity Clauses in Singapore Commercial Contracts
  11. What are Warranties, Conditions and Innominate Terms?
  12. Implied Terms: Filling in "Gaps" in a Contract
  13. Breach of Contract in Singapore
  14. Using Force Majeure/Frustration to Escape Contracts in Singapore
  15. What is the governing law of a contract?
  16. Punitive Damages in Singapore Contract Law
Common Contractual Issues
  1. Can I compel another party to honour an agreement?
  2. Contracting via Electronic Communications
  3. Assignment and Novation: Transferring Contracts in Singapore
  4. 7 Issues to Consider Before Being a Loan Guarantor in Singapore
  5. Calls on Performance Bonds in Construction Disputes: What to Do